Judge Denies Tribes' Emergency Bid to Halt Dakota Pipeline Construction

This version of Judge Denies Tribes Emergency Bid Halt Dakota Pipeline Construction N720451 - Breaking News | NBC News Clone was adapted by NBC News Clone to help readers digest key facts more efficiently.

The Standing Rock and Cheyenne River Sioux tribes sought a restraining order against Dakota Access and the Army Corps of Engineers last week.
Image: DAPL opposition camp
Crews remove waste from an opposition camp against the Dakota Access Pipeline near Cannon Ball, North Dakota last week.Terray Sylvester / Reuters

A federal judge denied an emergency bid Monday to temporarily halt construction of the Dakota Access Pipeline, court documents show.

The temporary restraining order, which was sought on Thursday by Sioux Tribe members in U.S. District Court in Washington, D.C., claimed that the 1,172-mile pipeline could damage water used in sacred Lakota ceremonies, the documents say.

Judge James Boasberg said at a hearing that damage couldn't occur until oil was flowing through the 30-inch pipeline, The Associated Press reported.

Boasberg ordered the company behind the pipeline, Dakota Access, to provide weekly updates about when oil is expected to reach the 370,000-acre Oahe reservoir, whose shores are partly home to the two tribes that filed the emergency order — the Standing Rock and Cheyenne River Sioux tribes.

Image: DAPL opposition camp
Crews remove waste from an opposition camp against the Dakota Access Pipeline near Cannon Ball, North Dakota last week.Terray Sylvester / Reuters

Last week, Cheyenne River Sioux Chairman Harold Frazier described water from the Missouri River, which flows through the reservoir, as a "central element of our Lakota spiritual beliefs."

"That water is our life," he said in a statement. "It must be protected at all costs."

Lawyers for Dakota Access filed documents Monday calling the tribes' religious claims "exceedingly tardy" and saying the harm cited by the tribes didn't meet the standards of a restraining order.

A hearing on another effort to block the pipeline is scheduled for Feb. 27.

Related: Dakota Access Pipeline: What's Behind the Protests?

The denial came five days after Dakota Access announced that the U.S. Army Corps of Engineers had granted the company a roughly one-mile easement that runs beneath the Missouri River and will allow the project's completion.

In December, under President Barack Obama, the Army Corps denied the easement, saying an alternative route should be explored.

That decision came after months of protests from Sioux tribe members and others who called themselves "water protectors." The protests sometimes turned violent, and authorities were accused of using excessive force and trying to criminalize activism.

Pipeline supporters have consistently argued that it will provide jobs and money to local economies.

×
AdBlock Detected!
Please disable it to support our content.

Related Articles

Donald Trump Presidency Updates - Politics and Government | NBC News Clone | Inflation Rates 2025 Analysis - Business and Economy | NBC News Clone | Latest Vaccine Developments - Health and Medicine | NBC News Clone | Ukraine Russia Conflict Updates - World News | NBC News Clone | Openai Chatgpt News - Technology and Innovation | NBC News Clone | 2024 Paris Games Highlights - Sports and Recreation | NBC News Clone | Extreme Weather Events - Weather and Climate | NBC News Clone | Hollywood Updates - Entertainment and Celebrity | NBC News Clone | Government Transparency - Investigations and Analysis | NBC News Clone | Community Stories - Local News and Communities | NBC News Clone